Electric hoist gantry crane matters Completion Acceptance

Equipment factory, the factory in accordance with professional standards crane "JB1306-84 crane technical conditions" and "JB/T5663.1-91 electric hoist gantry crane Types and basic parameters" "JB/T5663.2-91 electric hoist gantry crane technical conditions ", a series of quality checks and running test (depending on the device at the factory as part of the conditions of the test or the entire organization crane test), that qualified and granted a certificate of compliance.

To ensure that the use of units installed last  Steel crane   erected to meet the requirements, and use of the formal use of the crane before, based upon the relevant provisions of the first running test.

After the test run, the installation unit should hand over the  jib crane  handling procedures, hand over the acceptance documentation shall include:

A crane operation test record sheets (with attachments).

2, cranes hand over a single (with attachments).

3, crane production certificate (with attachments).

eot crane operation test record sheets, installation and use of units should be armed with one, if the machine is defective, whether or not being repaired, shall be registered in the record list, as the original basis.