santo gantry crane

2013年7月26日星期五

Overweight bridge crane inspection and testing machines and precautions

(1) Under normal circumstances,  bridge crane  shall annually conduct an inspection.
(2) Where a new installation, repair, alteration, normal use of time longer than two years, one year or disable  overhead bridge crane   lifting test procedures shall be in accordance with its test, after passing the order put into use.
(3) Load tests include no load test, static load test, dynamic test.

Testing and inspection work should pay attention
(A) inspection, testing must designate a person responsible for the work, the work must be done before beginning safety education relevant personnel to learn more about the procedures required, and should clear division of labor.
(2) in accordance with the mechanical, electrical, aerial  overhead bridge crane  safety procedures for final inspection
(3) start too, a small car. Commander must send a signal that it is safe only for
(4) except in the case of an emergency hazardous anyone can issue a stop signal, but only allowed to send an NIE commander commanding signal.
(5) test, the officer should stand in a safe position.
(6) should be developed in case of danger emergency emergency safety measures.

没有评论: